August 1, 2009 at 11:03 am
Symptom
In the material price analysis, for a material with the price control “3S”, the system also displays the document of an order settlement posted to a prior period in the current period. This is incorrect.
Other terms
ACTORDER, ACTCCS, KO88, CO88
Reason and Prerequisites
The material ledger and actual cost component split are active. The incorrectly [...]
July 23, 2009 at 9:08 am
Symptom
An internal error occurs for a goods receipt for a production order because globally buffered data is inconsistent.
Other terms
CO88, KO88, C+099, C+ 099
Reason and Prerequisites
There is a program error.
Solution
Implement the attached corrections.
July 2, 2009 at 8:55 am
Symptom
After you implement Note 1280358, the costs of a combined order are not settled completely.
Other terms
CO8B, KO88, settlement, combined order, default rule, PP5, PP6
Reason and Prerequisites
The settlement is a periodic settlement with the default rule PP6. You have implemented Note 1280358.
Solution
Implement the program corrections.
June 26, 2009 at 9:53 pm
Symptom
In a repeated periodic settlement of an order header, the system completes the settlement without any error messages and generates a settlement document even if no changes (new cost, change of delivery quantity) have been made since the last settlement.
The generated settlement document results in a total of zero and the system does [...]
June 23, 2009 at 3:42 am
Symptom
When you try to close a CO object after changeover to the euro, the system generates one of the error messages KO115, KO450, KO451 or KD276. The corresponding balances are rounding differences which were caused by the changeover to the euro.
Other terms
KO88, CO88, CJ88, CJ8G, VA88, KO02, CJ02, archiving, deletion flag, DLFL, CLSD, [...]
June 23, 2009 at 3:41 am
Symptom
You want to settle an order or WBS element to a G/L account that at the same time is also a cost element in CO. The system generates error message KI235 “Account & requires an assignment to a CO object”.
In this case an additional CO account assignment is (for example, cost center) is necessary [...]
June 23, 2009 at 3:23 am
Symptom
The RAFABNEW program does not generate any new depreciation areas for assets under construction for investment measures.
Other terms
XINVM, assets under construction, KO88, KO8G, CJ88, CJ8G
Reason and Prerequisites
It is not usually necessary to create a new depreciation area for assets under construction, since these fixed assets are not depreciated. During the final settlement, the new depreciation [...]
June 23, 2009 at 3:22 am
Symptom
You want to settle an order or WBS element to a G/L account that at the same time is also a cost element in CO. The system generates error message KI235 “Account & requires an assignment to a CO object”.
In this case an additional CO account assignment is (for example, cost center) is necessary [...]