July 27, 2009 at 5:56 am
Symptom
You use the actual costing and want to activate the actual cost component split.
Other terms
CNACT, ACTCCS, actual cost component split
Reason and Prerequisites
In the standard cost estimate, you have not defined any cost component structure yet.
Solution
In order to avoid problems after the activation of the actual cost component split, the new cost component structure must fulfill [...]
July 17, 2009 at 7:02 pm
Symptom
You execute or reverse the distribution of a cost object hierarchy. Sometimes the program terminates with the message FB_COMMON_MESSAGES.
Other terms
KKPX, KKPY, reversal, dump, MESSAGE_TYPE_X, FB_COMMON_MESSAGES, SAPLFAGL_COFI_ONLREC, LFAGL_COFI_ONLRECF22, PUT_FINAL_DOCNRS_INTO_TRACE, SAPMKKPA. RKKPAB03, actual cost distribution
Reason and Prerequisites
This was caused by a program error.
Solution
Implement the program corrections.
July 17, 2009 at 5:45 pm
Symptom
In transaction OKTZ you assign organizational units to cost component structures so different cost component structures are valid for the currencies or valuations managed in the material ledger.
Other terms
ACTCCS, actual cost component split, MLCCS_STARTUP, CKMLKEV
Reason and Prerequisites
For the actual cost component split the same settings must be valid for the cost component split [...]
July 7, 2009 at 9:53 am
Symptom
Although the tolerance limit for the consistency check is exceeded when importing the cost component split from Cost Center Accounting, the cost component split is still transferred.
Other terms
ACTCCS, actual cost component split, CKML_LA_GET_ACTIVITY_PRICES
Reason and Prerequisites
When calculating the relative deviation for values in currencies that have no decimal places, deviations smaller than 0.5 are [...]
July 7, 2009 at 7:39 am
Symptom
The price and cost component split data imported from the material ledger from the Cost Center Accounting does not match.
Other terms
ACTCCS, actual cost component split, CKML_LA_GET_ACTIVITY_PRICES
Reason and Prerequisites
The material ledger, actual costing with activity update and actual cost component split are active.